+44 (0)1268 777871Proteus Waterproofing was asked by Hilton Hotels to survey the Accommodation Annexe block at the Doubletree by Hilton Dunblane Hydro Hotel.
Core samples showed the existing roof was constructed of a metal deck, Rockwool insulation and waterproofed with a single ply. Core samples showed the insulation to be saturated with entrapped water caused by roof leaks through the single-ply membrane.
Key Challenges & Solutions
Proteus Waterproofing provided a bespoke roof specification to remove the existing roof coverings back to the structural deck and install a new Built-up Roof system comprising of new Rockwool
(non-combustible) insulation meeting the current building regulation requirement of 0.18 U-Value. The insulation was then waterproofed with the two-layer Proteus Pro-Felt® Ultima Plus system, BBA certified for a minimum 30 years.